Survey, Investigation, Design, Drawing and Construction Management of Precast Pretensioned Elevated Viaduct carrying a water discharge of 12.54Cumecs and a Road on top for a Length 12.5km under Mulwad LIS Stage III, in Bijapur District of Karnataka State. (EPC Mode Contract)
A 12.5 KM Length Viaduct Completed by our amazing team. It has been developed in Vijayapura Distrcit. It is a 30m span & Percast, Pre stressed U trough (230mton) Launched by cranes
About Project
Tidagundi Project
12.5 KM Viaduct Completed in Vijayapuri.
Project info
Client: Krishna Bhagya Jala Nigam Ltd., Government of Karnataka.Contractor: M/s Shankarnarayana Constructions Pvt. Ltd., Bangalore
Design Element: Casting Yard, U-Girder shuttering, Pier, Pier cap shuttering